What are the key milestones you need to achieve in order to complete your project successfully?
Milestone 1: Milestone 1:
Milestone Title
Project setup & planning, team formation and updating all essential specifications (Completion: End of month 1 of 12)
Milestone Outputs
- Project infrastructure and detailed planning of the project
- Updated Requirements Specification (originally established during Fund 11 Concept Phase)
- Updated Solution Specification (originally established during Fund 11 Concept Phase)
- Updated Business Model Specification (originally established during Fund 11 Concept Phase)
- Updated Website, Pitch-Deck and Pitch-Video (originally established during Fund 11 Concept Phase)
- Team in place
- Kickoff Event
Acceptance Criteria
- Project setup including project plan in GitHub completed
- Updated Requirements Specification Document released (V02.00)
- Updated Solution Specification Document released (V02.00)
- Updated Business Model Specification released (V02.00)
- Updated Website, Pitch-Deck and Pitch-Video (new release-versions)
- Roles defined, people allocated to roles, all properly documented
- Kickoff Event held (documented)
Evidence of Milestone Completion
We will deliver a brief video in which we will go through the individual outputs, the acceptance criteria and the evidence. The video will cover:
- Showing Github setup and the detailed project planning,
- Explaining the updates made to the Requirements Specification Document
- Explaining the updates made to the Solution Specification Document
- Explaining the updates made to the Business Model Specification Document
- Explaining the updates made to the Website, Pitch-Deck and Pitch-Video
- Introducing the team with all roles and allocated people
- Showing impressions and key-results of the Kickoff Event
Additionally, the validators will get links with read-access to the listed documents
Milestone 2: Milestone 2:
Milestone Title
First Iteration with focus on Design Thinking oriented Workshops, UX design and Solution Architecture with the main goal to get from the initially specified Baseline approaches to updated target designs based on workshops with deep Subject-Matter-Expert involvement (Completion: End of month 3 of 12)
Milestone Outputs
- Design Thinking Workshop 1
- Design Thinking Workshop 2
- Website Improvement Specification
- Business Processes, IAM and Tokenomics Specification Draft
- Frontend Development Specification
- Web3.0 Backend Development Specification Draft
- Migration and Implementation Specification (How to make this to the first Application Blueprint within the DLT360 Business Development Framework) Draft
Acceptance Criteria
- Design Thinking Workshop 1 completed and documented
- Design Thinking Workshop 2 complete and documented
- Released version of Website Improvement Specification (V01.00)
- Draft Version of Business Processes, IAM and Tokenomics Specification (V00.10)
- Draft Version of Frontend Development Specification (V00.10)
- Draft Version of Web3.0 Backend Development Specification (V00.10)
- Draft Version of Migration and Implementation Specification (V00.10)
Evidence of Milestone Completion
We will deliver a brief video in which we will go through the individual outputs, the acceptance criteria and the evidence. The video will cover:
- Present highlights and results of Design Thinking Workshop 1
- Present highlights and results of Design Thinking Workshop 2
- Explaining the content of the Website Improvement Specification (V01.00)
- Explaining the content of the Business Processes, IAM and Tokenomics Specification Draft (V00.10)
- Explaining the content of the Frontend Development Specification Draft (V00.10)
- Explaining the content of the Web3.0 Backend Development Specification Draft (V0.10)
- Explaining the content of the Migration and Implementation Specification Draft (V00.10)
Additionally, the validators will get links with read-access to the listed documents
Milestone 3: Milestone 3:
Milestone Title
Rapid Prototyping of Demo Versions of Frontend (UX / UI), simulated Backend, and Tokenomics-Concept. Second Iteration of Solution Architecture and Expert Workshops
(Completion: End of month 7 of 12)
Milestone Outputs
- Updated Website
- Rapid Prototype of Application Frontend Demo Version
- Rapid Prototype of Web3.0 Backend Demo Version (simulation mode)
- Updated Requirements Specification
- Updated Solution Specification
- Updated Business Model Specification
- Updated Pitch-Deck and Pitch-Video
- Expert Workshop 1
- Expert Workshop 2
- Updated Website Improvement Specification
- Updated version of Business Processes, IAM and Tokenomics Specification
- Updated version of Frontend Development Specification
- Updated version of Web3.0 Backend Development Specification
- Updated version of Migration and Implementation Specification
Acceptance Criteria
- Released version of updated Website
- Rapid Prototype of Application Frontend Demo Version available
- Rapid Prototype of Web3.0 Backend Demo Version (simulation mode) available
- Updated Requirements Specification (V02.10)
- Updated Solution Specification (V02.10)
- Updated Business Model Specification (V02.10)
- Updated Pitch-Deck and Pitch-Video
- Expert Workshop 1 completed and documented
- Expert Workshop 2 completed and documented
- Updated Website Improvement Specification (V01.10)
- Updated version of Business Processes, IAM and Tokenomics Specification (V0.20)
- Updated version of Frontend Development Specification (V00.20)
- Updated version of Web3.0 Backend Development Specification (V00.20)
- Updated version of Migration and Implementation Specification (V00.20)
Evidence of Milestone Completion
We will deliver a brief video in which we will go through the individual outputs, the acceptance criteria and the evidence. The video will cover:
- Detailed explanation of the updated Website
- Detailed demonstration of the Application Frontend Demo Version
- Detailed demonstration of the simulated Web3.0 Backend Demo Version
- Explain the updated Requirements Specification (V02.10)
- Explain the updated Solution Specification (V02.10)
- Explain the updated Business Model Specification (V02.10)
- Explain the updated Pitch-Deck and Pitch-Video
- Present highlights and results ofExpert Workshop 1
- Present highlights and results ofExpert Workshop 2
- Explain the updated Website Improvement Specification (V01.10)
- Explain the updated Business Processes, IAM and Tokenomics Specification (V00.20)
- Explain the updated Frontend Development Specification (V01.10)
- Explain the updated Web3.0 Backend Development Specification (V00.20)
- Explain the updated Migration and Implementation Specification (V00.20)
Additionally, the validators will get links with read-access to the listed documents and applications.
Milestone 4: Milestone 4:
Milestone Title
MVP Demo Version Development, including Backend Simulation of IAM, Smart Contracts, Tokenomics (Completion: End of month 11 of 12)
Milestone Outputs
- MVP Version of the Website, supporting the simulation of Business Processes, IAM and Tokenomics
- MVP Demo Version of Application Frontend
- MVP Demo Version of Web3.0 Backend (simulated)
- Updated Development Specification for future Product Development
- Business Processes, IAM and Tokenomics Documentation (V00.30)
- Frontend Development Documentation (V00.30)
- Web3.0 Backend Development Documentation (V00.30)
- Migration and Implementation Documentation (V00.30)
- Internal Security Review Summary (V00.10)
- Internal Legal Review Summary (V00.10)
Acceptance Criteria
- MVP release of the Website available
- MVP release of Application Frontend Demo available
- MVP release of Version of simulated Web3.0 Backend Demo available
- Development Documentation available
- Internal Security Review Summary documented
- Internal Legal Review Summary documented
Evidence of Milestone Completion
We will deliver a brief video in which we will go through the individual outputs, the acceptance criteria and the evidence. The video will cover:
- Detailed explanation of the MVP Website
- Detailed demonstration of the MVP Application Frontend Demo
- Detailed demonstration of the simulated MVP Web3.0 Backend Demo
- Explain Development Documentation (all in V00.30 Version)
- Explaining Internal Security Review Summary
- Explaining Internal Legal Review Summary
Additionally, the validators will get links with read-access to the listed documents and applications.
Final Milestone: Final Milestone
Milestone Title
Complete all deliverables, MVP Demo Version released and functional, Ready for customer PoC, Piloting and Roll-outs and formal closing of the project (Completion: End of month 12 of 12):
Milestone Outputs
- Release Requirements Specification (V03.00)
- Release Solution Specification (V03.00)
- Release Business Model Specification (V03.00)
- Release Website supporting the MVP Demo
- Released Pitch-Deck and Pitch-Video
- Released Development Specification for future Product Development
- Business Processes, IAM and Tokenomics Documentation (V01.00)
- Frontend Development Documentation (V01.00)
- Web3.0 Backend Development Documentation (V01.00)
- Migration and Implementation Documentation (V01.00)
- Internal Security Review Summary (V01.00)
- Internal Legal Review Summary (V01.00)
- Internal Project Closing
- External Project Closing
- Closeout Report
- Closeout Video
Acceptance Criteria
- Release Requirements Specification (V03.00) available
- Release Solution Specification (V03.00) available
- Release Business Model Specification (V03.00) available
- Release Website supporting the MVP Demo available
- Released Pitch-Deck and Pitch-Video available
- Released Development Specification for future Product Development
- Business Processes, IAM and Tokenomics Documentation (V01.00) available
- Frontend Development Documentation (V01.00) available
- Web3.0 Backend Development Documentation (V01.00) available
- Migration and Implementation Documentation (V01.00) available
- Internal Security Review Summary (V01.00) available
- Internal Legal Review Summary (V01.00) available
- Internal Project Closing done
- External Project Closing
- Closeout Report submitted
- Closeout Video submitted
Evidence of Milestone Completion
We will deliver a brief video in which we will go through the individual outputs, the acceptance criteria and the evidence. As evidence we will provide:
- Showing and explaining Requirements Specification (V03.00)
- Showing and explaining Solution Specification (V03.00)
- Showing and explaining Release Business Model Specification (V03.00)
- Showing and explaining Website supporting the MVP Demo
- Showing and explaining Pitch-Deck and Pitch-Video
- Showing and explaining Development Specification for future Product Development
- Business Processes, IAM and Tokenomics Documentation (V01.00)
- Frontend Development Documentation (V01.00)
- Web3.0 Backend Development Documentation (V01.00)
- Migration and Implementation Documentation (V01.00)
- Showing and explaining Internal Security Review Summary (V01.00)
- Showing and explaining Internal Legal Review Summary (V01.00)
- Sharing the results of the internal Retrospective Meeting
- Closeout Report submitted, Closeout Video presented and submitted
We will also provide the required links for allowing deeper-going review